This article explains how to connect Procore to Adaptive and sync your project data, including budgets, change orders, and purchase orders.
1. Connecting Procore to Adaptive
To connect your Procore account:
Navigate to the Procore integration page in Adaptive (Settings -> Procore)
Sign in to Procore using your normal credentials
You will be redirected to Adaptive after authentication
Select your company from the list
2. Selecting Data to Sync
After selecting your company, choose which data you want to sync from Procore to Adaptive:
Budgets
Prime Contract
Change Orders
Commitments
Select or unselect each option based on your needs, then click Sync.
Important: Syncing budgets from Procore will override any budget data in Adaptive. Ensure you want to replace your current Adaptive budget before selecting the Budgets option.
3. Viewing Synced Data
After syncing completes, you'll see four tabs:
Jobs
Cost Codes
Vendors
Commitments
4. Jobs Tab
External Links: Each job includes an external link that directs you to the corresponding Procore project page.
Auto-Matching Rules: Jobs are automatically matched during sync using:
Project number
Company name
Full project name
Jobs with matching criteria will be linked automatically. For example, if the project number matches between Procore and Adaptive, the job will be matched even if the names differ slightly.
Unlinking and Relinking: To unlink a job:
Click the unlink action in the job row
Confirm in the popup window
To relink, use the link action
5. Cost Codes Tab
Cost Code Variants: Procore cost codes may have multiple variants. These variants are merged together and mapped to a single Adaptive item.
Unlinking and Relinking: Cost codes can be unlinked and relinked using the same process as jobs.
6. Vendors Tab
Unlinking and Relinking: Vendors can be unlinked and relinked using the unlink action in each vendor row.
7. Budget Syncing
Budget Components: Procore budgets sync to Adaptive with three components:
Original Budget: The initial budget set up in the project
Budget Modifications: Internal modifications that move amounts between cost codes
Approved Change Orders (CEOs): External contract changes that appear as change orders in Adaptive
Real-Time Sync: Budget changes made in Procore sync to Adaptive in real-time. When you update a budget line in Procore and refresh the Adaptive page, the changes appear immediately.
Change Order Lines: Change orders are pulled as individual lines and displayed in the Changes section of your budget.
Note: Syncing budgets from Procore replaces existing Adaptive budget data for the connected projects.
8. Commitments (Purchase Orders)
Viewing Commitments: All Procore commitments are pulled and displayed in the Commitments tab. Correctly mapped commitments create corresponding Adaptive purchase orders.
Change Orders for Purchase Orders: Procore allows change orders on purchase orders. Since Adaptive does not have separate change orders for purchase orders, all changes are merged into a single purchase order:
The original purchase order lines are included first
Change order lines are added to the same purchase order
The total amount reflects the original value plus all change orders
Example:
Original PO: $192,000 with 6 lines
Change Order 1: +$7,000
Change Order 2: -$20,000
Final Adaptive PO: $179,000 with all original lines plus change order lines